Road and building updates
The Property and Facilities Division is responsible for the construction, refurbishment and maintenance of UQ property, facilities and grounds.
Keep up to date on major building works, road works and closures, events and shutdown disruptions on UQ sites.
If you're a staff member and would like to receive notification emails about specific buildings, please contact comms@pf.uq.edu.au to be added to the relevant distribution list.
View more information about projects and initiatives managed by the Property and Facilities Division.
St Lucia
The University will host the December 2026 graduations at St Lucia from Friday 11 December 2026 – Saturday 19 December 2026, with set up and pack down activities to occur in the week before and after.
Outlined below are details of the affected areas on campus, including parking and road closures.
Affected areas
Graduation ceremonies will be held in the UQ Centre followed by post-ceremony celebrations in the Great Court.
As a result, the following areas are likely to see an increase in activity and will be subject to some traffic restrictions:
We kindly request that noise, vehicle movement, and construction works in and around the affected areas be reduced to prevent disruptions.
During graduations, it will not be possible to accommodate other events and functions in Campbell Place, the Great Court or on the Forgan Smith lawns.
Road closures
As per previous years, road closures will be in place during graduations. These road closures are essential to reduce the risks associated with the large number of people and suppliers on campus.
Below is an outline of the affected roads that will be closed from Friday 11 December 2026 – Saturday 19 December 2026 (inclusive):
- Vehicle access to the Great Court will be closed for the week of graduations, including times between individual ceremonies.
- UQ Security will manage access for authorised and emergency vehicles only.
- Union Road will be fully closed to vehicles during the graduation ceremonies period. Please make alternative arrangements for any planned deliveries.
- UQ Security will manage access for authorised and emergency vehicles only.
If vehicle access to these areas is required during this period, please contact UQ Senior Events Officer Jo Plant as soon as possible.
Parking changes
There will be a number of temporary changes to parking on campus from Friday 11 December 2026–Saturday 19 December 2026 (inclusive), details as follows:
- Several car parks in Mansfield Place will be reserved for suppliers.
- Access to P10 UQ Centre Carpark and P10 Synthetic Fields Carpark will be via Sir William MacGregor Drive only.
P10 Aquatic Centre Carpark (outdoor) is permanently closed to enable construction of the new UQ Sport Fitness Centre.
Accessibility parking is available at P10 UQ Centre Carpark, Mansfield Place, University Drive, Slip Road and Staff House Road. For more information, see the accessible parking webpage.
Action needed
Where possible, we would be grateful if you could reschedule activities that may be impacted by the road closures and events occurring during graduations.
Please forward this information to external partners, clients and stakeholders who may be affected.
If you have any queries, please contact UQ Senior Events Officer Jo Plant.
If you would like further details on the ceremony schedule, please see the graduation webpage.
The University of Queensland will be hosting the December 2026 graduations at Gatton on Thursday 10 December 2026.
Please note the key dates, affected areas and road closures below.
Key dates
Set up: Monday 7 December – Thursday 10 December 2026
Ceremonies: Thursday 10 December 2025, 10am, 12pm and 2pm
Pack up: Thursday 10 December – Friday 11 December 2026
If you would like further details on the ceremony schedule, please see the graduation webpage.
Affected areas
- Gymnasium
- Dining Hall and Central Walkway
- Morrison Hall
- Foundation Building
- Intercampus shuttle bus stop
Graduation ceremonies will be held in the Gymnasium followed by post-ceremony celebrations in the Dining Hall and the Central Walkway. Graduates and their guests will be present and moving around, increasing pedestrian traffic throughout these areas.
We request that noise, unnecessary vehicle movement and/or construction works in and around the affected areas are reduced to enhance our graduates' experience and minimise risk.
Road closures
Road closures will be in place during graduations due to increased pedestrian traffic. These road closures are essential to reduce the risks associated with the large number of people and suppliers on campus.
UQ Security will be on site managing the closures and allowing restricted access only to graduations providers during periods of low risk, and Emergency Services vehicles (if required).
Below is an outline of the roads that will be closed to vehicle access on Thursday 10 December 2026:
- Inner Ring Road from Morrison Hall to behind the Gymnasium
- Galletly Road around the Gymnasium
- The road behind the Gymnasium
- Access to the swimming pool car park will be one-way only.
Intercampus shuttle bus stop – temporarily moved
Due to the increased foot traffic on Inner Ring Road, the intercampus shuttle bus stop will be temporarily moved to the corner of Inner Ring Road and Chapel Hill Road on Thursday 10 December 2026.
Please feel free to forward this on to your external stakeholders who may be affected and please notify your relevant clients as required.
You are welcome to contact UQ Senior Events Officer Jo Plant should you have any questions.
We thank you for your cooperation in providing a safe and memorable experience for graduates and their guests.
Essential air-conditioning infrastructure upgrade works will be undertaken at Colin Clark (39), requiring crane operations, temporary road closures, pedestrian diversions and building access restrictions.
Affected areas
- Blair Drive
- Colin Clark (39)
Figure 1: Blair Drive Road closure with vehicle detour via Sir William MacGregor Drive.
When
- Start/Finish: Saturday 28 November 2026
- Times: 4.00am – 5.00pm
Work details
- Existing rooftop air-conditioning equipment will be removed and replaced as part of essential infrastructure upgrades.
- Blair Drive will be closed during the crane operations.
- There will be no access to Colin Clark (39) between 4:00 am and 5:00 pm.
- Pedestrian diversions, traffic control measures and exclusion zones will be in place around the work area. Alternative pedestrian and vehicle routes will be available.
- Traffic controllers and spotters will be on site to safely manage vehicle and pedestrian movements.
Contact
Lisa Filmalter, Senior Mechanical Infrastructure Engineer
- Phone: 0437 623 856
- Email: lisa.filmalter@uq.edu.au
Pedestrian access through Forgan Smith Tower (Level 2) from University Drive is closed until at least mid-November for safety during the works. Alternative pedestrian routes are available via the Walter Harrison Law and Forgan Smith Tower East entrances. Forgan Smith Tower Level 2 remains accessible via the Great Court cloisters, with signage in place to direct pedestrians.
There will be temporary increases in noise, vehicle movements and changes to access arrangements during this period. We apologise for any inconvenience and the contractor will take steps to minimise impacts as much as possible.
Please note that no noisy works will be carried out during examination and graduation periods.
Affected areas
- Forgan Smith Building (1) and surrounding areas
- Forgan Smith Building (West)
- Forgan Smith Building (East)
- The Great Court
- Feeny Way and University Drive
- Michie Building (9)
- Duhig Tower
- Nearby retail facilities
When
- 13 October to late November 2026 (scaffolding installation from 14 October)
- Work hours: 6:00am to 4:30pm
Work details
- There will be increased truck movements along University Drive and within the Great Court to facilitate the delivery of scaffolding materials. Where possible, deliveries will occur before 7am to minimise disruption to university operations. A traffic management plan will be in place to ensure the safe movement of pedestrians and vehicles.
- Fully fenced laydown areas will be established on University Drive (within the GoGet parking bay) and in the Great Court. These areas will remain in place for the duration of the works.
- From 13 to 17 October, pedestrian access through Forgan Smith Tower (level 2) will be unavailable. During this period, pedestrians are encouraged to walk through the Michie Building (9) or the Forgan Smith Tower East entrance.
- Scaffolding installation will commence from 14 October, beginning at the lower levels and progressively extending to the full height of the tower. Installation of the complete scaffold structure is expected to take approximately six weeks.
- During installation, there will be periods of elevated noise, including banging and clanging associated with the assembly of scaffold components.
- Once fully erected, the upper levels of the scaffold will be fitted with custom-designed screening.
- A mobile crane will be used on Thursday 5 November 2026 to support with scaffolding installation. To safely undertake this activity, the tower and surrounding areas will need to be temporarily vacated and impacted teams have been contacted directly. University Drive and the neighbouring footpath will be temporarily closed while these works are underway and traffic control will be in place to direct motorists and pedestrians.
Additional information
Please note that delivery and vehicle access on the Great Court side of Forgan Smith Tower will be affected for the duration of the remediation project. If you require access to the area, please contact the project team to discuss alternative arrangements.
Contact
Michael Knight, Project Manager:
- Call: 0451 129 108
- Email: m.knight1@uq.edu.au
Figure 1: Annotated aerial map showing pedestrian access routes and temporary exclusion zones.
The University and UQ Union (UQU) are working together on a staged redevelopment of the Union Complex at St Lucia.
Main works to refurbish Building 21C will begin in October 2026. The University and its contractor are working closely with the UQU to coordinate main works and minimise impacts as much as possible.
This page will be updated with information about any parking, traffic and pedestrian changes as works progress.
Affected areas
- Building 21C, Union Complex and surrounding areas
When
- Main works: From October 2026
- Work will be carried out between 6am to 6pm, Monday to Friday (Saturday works as required).
Details and mitigation
Pedestrian access
- Pedestrian access to all three levels of the Union Complex will remain open via the Building 21C lift and stairs for the remainder of Semester 2, 2026.
- The stairs between level 2 and 3 of the Union Complex will be temporarily closed on Sunday 15 November while scaffolding and screening is installed around them. Pedestrian access will be maintained to these levels via the lift, and the stairs will reopen on Sunday afternoon once scaffolding is in place.
- Access is expected to change during the summer holidays after Semester 2, with details to be shared prior to Semester 1, 2027.
- The stairs in front of the Schonell Theatre (level 2) will remain closed.
Parking and travel
- The motorcycle parking zone and reserved car parking zone outside Building 21C will remain closed as these areas are part of the work site.
- Alternative accessible (PWD) car parks are available at the end of Staff House Road or underneath the UQ Centre. For alternative locations and maps, visit the accessible parking page.
- End of trip facilities are currently available via an alternative entrance on level 1 of the Union Complex (located underneath the stairs and opposite the existing lift). Users will be notified ahead of upcoming changes.
- Visit Cycling at UQ for alternative bike racks and repair stations.
Construction management
- There will be increased truck movements via Union Road and Campbell Place.
- Traffic control and signage will be in place as part of a traffic management plan to ensure the safe movement of pedestrians and road users, in coordination with construction for the new Fitness Centre.
- Safety measures will include construction management plans, protective equipment, signage and barricades. Any asbestos-containing material will be wrapped before being removed from the building for disposal and managed in accordance with legislative requirements.
Contacts
For construction questions, contact projectcomms@uq.edu.au
From Monday 17 November 2025 there will be parking and traffic changes on Keith Street, St Lucia, to allow for works at the Playhouse Childcare Centre.
This includes intermittent road closures along Keith Street at various stages of works. During these times, a Stop/Go traffic arrangement will be in place to maintain safe traffic flow. A permit for these works has been approved by Brisbane City Council (RC-4061-3).
In addition, the undercover P7 carpark (approximately 30 bays) will be closed for approximately 12 months while works are underway.
The outdoor P7 carpark will remain open to the community.
Affected areas and details
- Traffic control will be in place on Keith Street, St Lucia
- The undercover carpark under the Playhouse will be closed
- The footpath on one side of Keith Street will be closed. For safety, pedestrians will be directed to use the opposite side.
When
Monday 17 November (for approximately 12 months)
Contact
For any enquiries, contact PF Assist:
- Email: pfassist@pf.uq.edu.au
- Call: (07) 3365 2222
UQ Sport Fitness Centre construction
UQ is building a new multi-level UQ Sport Fitness Centre as part of its 35-hectare Sport and Recreation Precinct at St Lucia.
During construction, there will be a number of parking, traffic and pedestrian changes in the area. Works will begin from 30 June 2025, with expected completion in 2027.
Affected areas
- The P10 Aquatic Centre Carpark is permanently closed.
- All vehicles entering and exiting the P10 UQ Centre and Synthetic Playing Fields Carpark must use Sir William MacGregor Drive. Vehicle access via Union Road is no longer available.
- Two accessible (PWD) car parks have been temporarily relocated to the front of the UQ Sport Aquatic Centre on Union Road. During main construction, these are expected to be moved to the P10 UQ Centre Carpark due to increased truck movements. Alternative PWD car parks are also available at the P10 UQ Centre and P10 Synthetic Fields Carparks. For alternative locations and maps, visit the accessible parking page.
- A section of the P10 UQ Centre Carpark will be allocated to Aquatic Centre customers.
- Pedestrian access from the P10 UQ Centre Carpark to Union Road, including the UQ Sport Aquatic Centre, is via the stairs or lift in the UQ Centre Carpark and signage is in place.
- A section of car parks along Sir William MacGregor Drive will be closed when required as a truck loading zone.
- Some red zone car parks along Blair Drive have been permanently changed to yellow zone, 2-hour parking (zone number 1472400) to support short-term parking access near the Aquatic Centre.
- A temporary workspace has been established in a fenced-off area in front of the HMBS building. Temporary pedestrian detours will be in place between Union Road and Blair Drive, though access between Union Road and Blair Drive will always remain open. Pedestrians should follow the signage in the area.
When
- From 30 June 2025, ongoing until 2027
- Work will be carried out from 6am to 6pm, Monday to Friday (Saturday works as required)
Details and mitigation
- We acknowledge the impact on people who park in this area and are reviewing parking options across the campus to optimise availability.
- A 5 minute passenger drop off zone has been introduced on Blair Drive for Aquatic Centre users.
- A section of the P10 UQ Centre car park will be allocated to Aquatic Centre users and signage will be put in place (please be aware this allocation may change during major events).
- Traffic control and signage will be in place as part of a traffic management plan to ensure the safe movement of pedestrians and road users.
- A construction management plan will be in place to ensure safety and minimise noise, dust, vibration and other disruptions as much as possible.
- Notifications will be provided to neighbouring buildings and UQ Sport members ahead of works commencing.
- As construction progresses, there will be changes to traffic and pedestrian access on Union Road. Updates will be published here and notifications will be provided to nearby stakeholders prior to these changes.
Map
This map provides an overview of parking, traffic and pedestrian changes in the area. It will be updated as construction progresses.
Fitness Centre construction, Phase 1
Contacts
- For construction questions, contact projectcomms@uq.edu.au
- Contact UQ Sport for membership or other facilities information